Service Standards


In the Annex to the Petition

1. New Dated Deed (for the last 6 months)
2. Building Permit
3. A letter from the Provincial Directorate of SSI, indicating the m2 related to the construction, that there is no debt - ASIL
4. The inion is suitable for health in the use of the building (near H.Güldüoğlu ASM- Seyyid Burhaneddin Hz. Tomb)-ASIL
5. The Shelter is Suitable letter from the Shelter Commission (OIZ Director)- MAIN
6. Real estate determination report from the municipality (Hacılar Bld.-Melikgazi Bld.)- ASIL
7. OIZ Director From the Water - Sewerage Directorate
- Fire Installation certificate of conformity
- Sewer - Rain Network connection conformity certificate

When the above documents are completed, the building will be examined by a technical committee formed by our region and it will be determined whether it was built in accordance with the license and its annexes. If the building is built in accordance with the permit;

8. Letter from the tax office stating that the fee has been paid (to be sent with a letter from the O.S.B.)

Transaction No: 3 - Documents Required for Business Opening License

APPLICATION/ DECLARATION FORM FOR OPENING A WORKPLACE AND WORK LICENSE;

1- Copy of Title Deed (If Tenant, Title Deed and Rental Contract)
2- Copy of building occupancy permit
3- Fire adequacy report from OIZ Fire Brigade
4- EIA positive or EIA not required document (Provincial Directorate of Environment and Urbanization)
5- Temporary Activity Certificate or Environmental Permit (Provincial Directorate of Environment and Urbanization)
6- Is there a Wastewater Connection Permit? (Organized Industry Directorate)
7- Occupational Safety Specialist and Occupational Physician report and contracts
8- Situation Plan
9- Machine layout
10- Capacity report (Chamber of Industry)
11- Chamber of Industry or Chamber of Commerce Registration Certificate
12- Copy of tax plate
13- Establishment Announcement, Authorization Certificate and Signature Circular (for companies)
14- Identity, Mastery Certificate and Chamber of Craftsmen Registration Certificate (for individuals)
15- Responsible Manager Agreement and Copy of Diploma (For 1st class GSM and chemical, food, etc. workplaces)
16- Fee receipt (The letter to be written from OIZ will be paid to the relevant municipality)

  Transaction No: 4 - Natural Gas Subion

1. The printed petition (required information table for natural gas subion) to be received from our region will be filled in with the industrialist and the natural gas interior installation company appointed by the industrialist.
2. Upon the submission of the petition to our Region, a letter of guarantee for the natural gas deposit, the amount of which has been notified to the industrialist, or the receipt of cash deposited in the accounts of our Region
3. If the owner is a company, the authorization certificate of the persons authorized to sign
4. Copies of identity cards of authorized signatories

Completion Time at the latest : 2 Days

Transaction No: 5 - Electricity Subion

1. Petition
2. If the Official Tenant, the decision letter of the Board of Directors
3. Approved Electricity Project and Provisional Acceptance Minute (In the first power supply)
4. Connection Fee (at first energizing)
5. Electricity Security Fee (Cash or a definite and indefinite letter of guarantee)
6. Signature circular if the Owner is a Company, Signature statement if the Owner is a person
7. Copies of identity cards of authorized signatories
8. Stamp
9. No Debt Certificate From Our Accounting Unit

Completion Time at the latest : 2 Days

Transaction No: 6 - Water Subion

1. Petition
2. If the Official Tenant, the decision letter of the Board of Directors
3. Signature circular if the Owner is a Company, Signature statement if the Owner is a Person
4. Copies of identity cards of authorized signatories
5. Stamp
6. No Debt Certificate from our Accounting Unit

Completion Time at the latest : 1 Day

Process No: 7 - Sewer Connection

1. Petition

Completion Time at the latest : 2 Days

Transaction No: 8 - Discharge Permit

1. Petition
2. Submission of in-house sewerage and stormwater network plans in the annex of the petition

Completion Time at the latest : 2 Days

Transaction No: 9 - Providing Fire Training

1. Petition

Completion Time at the latest : 2 Days

If a document other than the above-mentioned documents is requested during the application, the service is not completed within the specified time despite the application with the complete document, or it is determined that some services are not available in the table above, apply to the first application or the second application site.